Expansion of the Bezledy Road Border Crossing
Status: Completed
Project: Execution of electrical and telecommunication works as part of the "Expansion, Reconstruction, and Modernization of the Bezledy Road Border Crossing."
Client: Industrial Construction Enterprise Holding "Przemysłówka"
Contractor: T4B sp. z o.o.
Contract Value: 5,5 mln PLN
Completion period: 13.08.2014 r. - 22.12.2014 r.
Scope of work:
• Lightning protection system installation and dismantling
• Power supply for customs clearance platform
• Reconstruction and securing of the existing electrical infrastructure
• Electrical installations dismantling in control pavilions
• Additional works related to traffic management during construction
• Electrical installations under the shelter
• Construction of a cabling infrastructure
• Telecommunication backbone network construction
• Structured cabling
• CCTV system reconstruction
• Access control system installation in Customs Service pavilions
• SOC system reconstruction and temporary relocation of SOC-O systems during the construction process
• Lightning protection system installation and dismantling
• Power supply for customs clearance platform
• Reconstruction and securing of the existing electrical infrastructure
• Electrical installations dismantling in control pavilions
• Additional works related to traffic management during construction
• Electrical installations under the shelter
• Construction of a cabling infrastructure
• Telecommunication backbone network construction
• Structured cabling
• CCTV system reconstruction
• Access control system installation in Customs Service pavilions