EXPANSION OF THE ELECTRICITY QUALITY MONITORING SYSTEM
Status: In progress
Project: Expansion of the Electricity Quality Monitoring System
Client: Polskie Sieci Elektroenergetyczne SA
Contractor: T4B sp. z o.o.
Contract Value: 30 mln PLN
Completion period: 31.05.2021 r. - 31.05.2024 r.
Scope of work:
• Comprehensive execution of the SMJEE infrastructure, including the procurement, delivery, and installation of 140 Electricity Quality Analyzers (AJEE), auxiliary devices, and measurement cabinets; installation of cabling and commissioning of electricity quality measurement systems at 54 PSE sites across Poland;
• Allocation of AJEE between facilities to ensure uniform technical solutions at each station;
• Delivery, installation, and commissioning of IT systems, including the implementation of SMJEE central unit software at both the primary and backup Data Processing Centers, along with applications for an anticipated 50 users.
• Comprehensive execution of the SMJEE infrastructure, including the procurement, delivery, and installation of 140 Electricity Quality Analyzers (AJEE), auxiliary devices, and measurement cabinets; installation of cabling and commissioning of electricity quality measurement systems at 54 PSE sites across Poland;
• Allocation of AJEE between facilities to ensure uniform technical solutions at each station;
• Delivery, installation, and commissioning of IT systems, including the implementation of SMJEE central unit software at both the primary and backup Data Processing Centers, along with applications for an anticipated 50 users.