T4B

T4B (as the lead) in a consortium with MERX Sp. z o.o. and PKP Energetyka S.A. signed another contract with the Podlaskie Provincial Office in Białystok for additional works as part of the “Design and Build” project titled “Adaptation of the Rail Border Crossing in Kuźnica Białostocka to Schengen Agreement Requirements – Phase I: Infrastructure.”

The contract included designing and installing 55 additional cameras for the surveillance system in special monitoring areas, covering the station area and inspection roads from 236.287 km to the State border. The work was completed in January 2011.