Status: Completed
Project: Execution of work as part of the project: "Expansion of the Medyka Road Border Crossing – garage building, clearance booths for the Border Guard and Customs Office, wooden dog kennels, and the expansion and modernization of steel canopies."
Client: Warbud SA
Contractor: T4B sp. z o.o.
Completion period: 27.06.2008 r. - 30.01.2009 r.
Scope of work:
• Electrical and telecommunication installations for the clearance booths and canopies for the Border Guard and Customs Office
• Supply and installation of barriers and tire killers
• Installation of lighting under the canopies for the additional clearance lanes
• Construction of new power supply lines
• Installation of OCR systems for 4 lanes
• Supply and installation of 10 cameras with a recorder
• Installation of access control systems
• Construction of telecommunication and electrical ductwork
• Installation of structured cabling
• Removal of existing electrical and telecommunication installations from the current canopies
• Reinstallation of electrical and telecommunication systems on the canopies
• Installation of internal lighting for a complex of 6 garages
• Preparation of design documentation for the project scope
• Expansion of the CCTV system on the canopies
• Installation of electrical systems in the kennel, garage, and service areas
• Expansion of the traffic control system
• Expansion of the SWOC and OCR systems
T4B Sp. z o.o., commissioned by Warbud S.A., executed the following work as part of the project: “Expansion of the Medyka Road Border Crossing – garage building, clearance booths for the Border Guard and Customs Office, wooden dog kennels, and the expansion and modernization of steel canopies”:
- Electrical and telecommunication installations for the clearance booths and canopies
- Supply and installation of barriers, tire killers, lighting, and OCR systems for 4 lanes
- Installation of 10 cameras, access control systems, structured cabling, and telecommunication/electrical ductwork
- Expansion of the CCTV system and traffic management system
The work was completed between June 27, 2008, and January 30, 2009.