T4B

T4B carried out works under a contract with the General Construction Company “Karwowski – Lipa” for telecommunication installations and the construction of telecommunication ductwork as part of the expansion of the Gołdap Road Border Crossing (Phase IIIJ).

The scope of work included:

  • Construction of telecommunication ductwork near pavilions No. 32 and 33, connected to the existing ductwork from previous phases
  • Installation of telecommunication systems (Passage Blocking System) in the buildings of the Border Guard and Customs Service within the agreed scope
  • Installation of telecommunication systems (Traffic Control System) on the loading and unloading platforms for heavy vehicle traffic

The work was completed at the end of 2013.