WASTEWATER TREATMENT PLANT – ŁÓDŹ
Status: Completed
Project: Sale, along with design documentation, installation, and commissioning of a centrifuge for dewatering fermented sludge.
Client: Group Wastewater Treatment Plant Sp. z o.o.
Contractor: T4B Sp. z o.o. (leader) in consortium with Varia Tech Sp. z o.o.
Contract Value: 1,1 mln PLN
Completion period: 6.07.2016 – 21.02.2017
Scope of work:
• Installation of a C4E-4/454 HTS centrifuge manufactured by Flottweg SE for dewatering fermented sludge
• Installation of accompanying equipment as part of the modernization of the Mechanical Sludge Thickening and Dewatering facility at the treatment plant
• Installation of a C4E-4/454 HTS centrifuge manufactured by Flottweg SE for dewatering fermented sludge
• Installation of accompanying equipment as part of the modernization of the Mechanical Sludge Thickening and Dewatering facility at the treatment plant