Wrocław University of Science and Technology – Electrical Installations
Reconstruction of the C-19, C-20, C-21 building complex of Wrocław University of Science and Technology along with land development and demolition of the technical support facility – electrical installations.
Contracting Authority:
Przedsiębiorstwo Budowlano-Konserwatorskie CASTELLUM Sp. z o.o.
Scope of work:
disassembly of existing electrical installations,
delivery, installation, measurements and commissioning of a transformer substation,
reconstruction of existing MV cable lines,
execution of power supply for buildings A, B and C and reconstruction of existing LV cable lines,
execution of external area lighting,
delivery, installation and commissioning of main switchboards RG1 and RG2,
fire switch,
delivery, installation and commissioning of electrical switchboards with UPS,
execution of cable routes, power cables and conductors,
installation of primary and emergency lighting including delivery and installation of luminaires,
execution of power installation and socket outlets,
compensation of inductive and capacitive reactive power,
execution of lightning protection, earthing and equipotential bonding.
Ver outros projetos
+700 especialistas ao seu dispor!
- Fornecedor líder de soluções abrangentes de informática, teletecnia, telecomunicações e energia
- Atuamos em múltiplos setores, incluindo utilidade pública, administração do Estado, defesa nacional, energia, telecomunicações, negócios e engenharia do ambiente
- Capacidade de conduzir projetos em grande escala, multinível e multifacetados
- Fornecedor líder de soluções abrangentes de informática, teletecnia, telecomunicações e energia
- Atuamos em múltiplos setores, incluindo utilidade pública, administração do Estado, defesa nacional, energia, telecomunicações, negócios e engenharia do ambiente
- Capacidade de conduzir projetos em grande escala, multinível e multifacetados